Building projects: your responsibilities explained
You do not have to be a construction expert to commission building work. But you do need to know who is responsible for keeping people safe and ensuring that your building complies with the rules.
Two sets of requirements are particularly important: CDM 2015 deals with managing construction health and safety; the Building Safety Act and Building Regulations dutyholder rules deal with the safety and regulatory compliance of buildings. They are related, but they are not the same thing.



Images are illustrative, generated for this guide. They do not show an actual accident, building failure, prosecution or OC Architects project.
1. CDM 2015 — why does it exist?
Construction can be dangerous. Workers may fall from height, be injured by unstable structures or encounter asbestos. Members of the public can also be hurt if a construction site is not properly managed. The Construction (Design and Management) Regulations 2015 (CDM) aim to prevent these risks by ensuring that health and safety is considered when a project is planned and designed, not just once the builders arrive.
If you commission building work as part of your business, you are generally a commercial client. You must make suitable arrangements for managing the project, allow sufficient time and resources, provide relevant information and appoint competent people.
Who does what?
Where more than one contractor is involved, or is reasonably foreseeable, the commercial client must appoint in writing a CDM Principal Designer to plan, manage, monitor and coordinate health and safety during the design and pre-construction stages, and a Principal Contractor to manage health and safety during construction. The Principal Designer does not replace the contractor’s responsibility for site safety.
What if nobody is appointed?
Imagine you are refurbishing a shop while other parts of the building remain occupied. A dangerous risk is missed, and someone is seriously injured. An investigation may ask whether the project was properly planned, whether risks were communicated and whether the client made the required appointments.
For a commercial client, failing to appoint a CDM Principal Designer when required means the client must fulfil that role’s statutory duties. Failure to appoint a Principal Contractor has a similar consequence. This is not automatic liability for every accident; the circumstances and actual breaches matter. But doing nothing is not a way of avoiding the duty.
Read HSE’s guide for commercial clients ↗ · CDM Regulation 5: appointments ↗
2. Building Safety Act and Building Regulations — why are these rules there?
The Grenfell Tower tragedy exposed serious problems with building safety and accountability. The Building Safety Act 2022 strengthened the system, and changes to the Building Regulations in England introduced clearer duties for clients, designers and contractors. The general dutyholder rules are not limited to high-rise buildings; they can apply to ordinary commercial conversions, refurbishments, extensions and new buildings where Building Regulations apply.
The aim is straightforward: building work should be designed and constructed to comply with applicable requirements such as fire safety, structure, ventilation, accessibility and energy efficiency. The right people need to coordinate the work and identify compliance problems before they become costly or dangerous.
Who is responsible?
Clients must make suitable arrangements and appoint competent people. Where more than one contractor is involved or reasonably foreseeable, a non-domestic client must generally appoint in writing a Building Regulations Principal Designer to plan, manage and monitor design work and coordinate designers for compliance, and a Building Regulations Principal Contractor to coordinate the building work for compliance.
What if nobody is appointed?
Imagine a commercial conversion where several designers and contractors are involved. After completion, serious fire-safety or structural shortcomings are discovered. The authorities may examine who was responsible for planning and coordinating Building Regulations compliance, whether competent people were appointed and whether the client fulfilled its own duties.
Where a non-domestic client fails to make a required Building Regulations Principal Designer or Principal Contractor appointment, regulation 11D(5) places the unfilled role’s duties on the client until an appointment is made. A breach of statutory requirements can result in enforcement action or prosecution. This does not mean the client is automatically liable for every building defect.
Government guide: duties and competence ↗ · Building Regulations 11D: appointments ↗
3. Real cases — what can happen when responsibilities are not met?
These are documented examples of enforcement and prosecution. They illustrate why client responsibilities matter. They are not claims that every case involved failure to appoint a Principal Designer.
CDM · HSE PROSECUTION · 2026
Asbestos disturbance during demolition
The HSE reported that Sohan Group Limited, the client, had not appointed a Principal Contractor on a demolition project involving asbestos. The investigation concerned the handling of asbestos and the competence of those undertaking the work. Read the HSE report for the precise offences and outcomes.
CDM / HEALTH & SAFETY · COURT CASE · 2023
Child seriously injured by a falling roof slate
During renovation of the Moonfleet Manor hotel, a falling slate seriously injured a three-year-old child. The client, CDM Principal Designer and Principal Contractor were all prosecuted for their respective failings. The client was fined £200,000, with additional costs, under the Health and Safety at Work etc. Act 1974. This demonstrates that appointing others does not remove the client’s own duties.
BUILDING SAFETY · ENFORCEMENT FRAMEWORK
Building Regulations: what happens when requirements are breached?
The Building Safety Regulator’s published enforcement policy explains how serious breaches may be investigated and, where justified, prosecuted. This is official enforcement guidance, not a claim that a particular client has been convicted solely for failing to appoint a Building Regulations Principal Designer.
4. Why are there two Principal Designers?
CDM Principal Designer
Coordinates health and safety in the design and pre-construction phase, including foreseeable construction risks.
Building Regulations Principal Designer
Coordinates design work so that it is planned, managed and monitored for Building Regulations compliance.
OC Architects’ architectural services
Our agreed architectural services are separate from these statutory Principal Designer appointments unless the relevant role is expressly included.
The same suitably competent organisation can sometimes undertake both Principal Designer roles, but each role needs to be properly identified and appointed. An architect does not automatically become responsible for both simply by preparing drawings.
5. A simple checklist before your project starts
- Confirm who the client is and who will make decisions.
- Identify how many contractors are likely to be involved.
- Ask who will act as CDM Principal Designer and Principal Contractor, if required.
- Ask who will act as Building Regulations Principal Designer and Principal Contractor, if required.
- Allow for the appointments in your budget and programme.
- Provide available surveys, drawings and information about the site and building.
- Check whether the project has additional higher-risk building requirements.
6. How OC Architects can help
We understand that many clients have never encountered these rules before. We can help you understand how they fit into your project and identify when additional specialist appointments should be considered.
Important — separate written appointment: OC Architects LLP’s standard commercial architectural services do not include appointment as CDM Principal Designer or Building Regulations Principal Designer. Either role is undertaken only where OC Architects LLP has expressly accepted that specific role in writing, identifying its scope and the project stage or stages covered. Any appointment is limited to the stages expressly agreed in that written appointment; it does not automatically extend to subsequent stages, construction or completion. The client remains responsible for ensuring the required statutory roles are filled throughout the project, including arranging any successor appointment when our agreed period ends. These limitations do not remove statutory duties arising from work we actually undertake.
This does not remove the statutory duties that apply to us as designers for the services we do undertake.
Official legislation and guidance
- HSE: commercial client responsibilities ↗
- HSE: CDM dutyholders explained ↗
- Construction (Design and Management) Regulations 2015 ↗
- Building Safety Regulator: Building Regulations duties ↗
- Building Regulations 2010, Part 2A ↗
- Building Safety Act 2022 ↗
A general guide for commercial clients in England, not a substitute for project-specific professional or legal advice. Reviewed October 2026. External sources open in a new tab.